The Shoaiba power and desalination complex on the Red Sea coast. Photo: Quality-Manager-Steal via Wikimedia Commons (CC BY-SA 4.0)
The kingdom has pulled a major Red Sea desalination plant for the second time in two years, before the state water authority signed the contract. It's a fresh sign the state is reworking big-ticket projects.
The Saudi Water Authority cancelled the tender for a 300 million litre-a-day seawater desalination plant in Yanbu, Indian contractor VA Tech Wabag said in a stock exchange filing at the weekend.
The contract was worth about one billion Riyal ($272 million). It covered design, engineering, construction and commissioning of the plant.
Second time round
Wabag first won the job in September 2024, when it was valued at $317 million. The authority cancelled that tender in December 2024, citing internal administrative procedures.
It then awarded the project to Wabag again in July 2025, for the same 300 million litre-a-day plant at a lower contract value of $272 million.
Wabag signed that contract and sent it to the Saudi Water Authority, but the authority never counter-signed it, so the project never formally started.
Bidders were told through Etimad, the government's tender platform, that the latest cancellation was due to "internal reasons attributable to the customer." Wabag said it is asking the authority for more clarity.
Wabag shares fell as much as 10% in Mumbai on Monday.
Why it matters
Desalination is at the heart of the kingdom's water security, and Yanbu is one of its main industrial hubs on the Red Sea.
Cancelling an awarded project twice, before the authority's signature was on the contract, will catch the eye of foreign contractors pricing Saudi work. It comes as contract awards lean toward oil deals while building projects lag, and as state-linked firms such as miner Ma'aden trim spending.