Photo: Aramco
Aramco has signed up one of its regular contractors to build out oilfield pipelines for at least three years without fixing a price, keeping crews on call as the Kingdom’s output recovers from the war.
Dammam-based GAS Arabian Services Co. signed a unit-rate contract with Aramco last week to install well sites, flowlines, trunk lines, laterals, headers, manifolds and transfer lines, along with their facilities, the company said in a filing on Sunday.
How it’s priced
There’s no headline value. Aramco pays agreed rates for each work order it issues, so the final figure depends on how much work it hands out.
The contract runs for three years, and Aramco can extend it by another 24 months at its own discretion.
A steady customer
It’s the latest in a run of Aramco work for the contractor. In April, GAS Arabian signed a long-term agreement to provide in-plant services across Aramco’s facilities for six years, extendable to 12.
In December last year it won a 21-month order worth more than a tenth of its 2024 revenue, which was about 1.1 billion Riyal ($290 million).
The bigger picture
Unit-rate deals let Aramco call in crews field by field without committing to a fixed bill. That flexibility counts after a year in which the war forced it to cut output and then ramp back up.
Saudi crude output jumped to about 8.4 million barrels a day in September from 6.2 million in August, and exports hit their highest since February. More wells and flowlines are the next step in keeping that recovery going.