Get Five free: the five Saudi business stories that matter, in your inbox by 7am. Subscribe →

Nabataean tombs at Hegra in AlUla

Nabataean tombs at Hegra, AlUla's top attraction. Photo: Basheer Olakara via Wikimedia Commons (CC BY 2.0)

AlUla, the desert heritage site in Saudi Arabia's northwest, wants private investors to fund the next stage of its airport as it moves from a state-built showcase toward a place that needs outside capital to grow.

The test for investors is whether visitor numbers can catch up with the ambition.

The Royal Commission for AlUla has put an airport expansion out to investors and is now taking bids, spokesman Abdulrahman Al-Tureiri told Al Arabiya in an interview on Tuesday. The package covers a second passenger terminal, a bigger air cargo area and a longer runway.

That comes months after the commission finished upgrades that lifted the airport's capacity to 700,000 passengers a year, from 400,000. The airport has handled international flights since March 2021, including from Qatar and Bahrain, plus seasonal routes from Jordan and Egypt.

The money so far

The commission has spent more than 10 billion Riyal ($2.7 billion) on basic infrastructure: power stations, water storage, roads and waste management, Al-Tureiri said. Two water stations are almost finished and three more are on offer to investors.

AlUla is targeting $10.9 billion of investment by 2030. Al-Tureiri wouldn't say how much it has raised so far, because talks are still under way.

The hotels coming

Three hotel projects are being built: a 215-unit Hyatt Place due next year, a Marriott project with about 250 units due in 2028, and Aman Hegra, with 72 hotel and residential units, signed on Monday and due in about 40 months.

Why it matters

Tendering the airport is the clearest sign yet of the shift: the commission built the foundations, and now it wants investors to build on top.

Demand is still modest. Hegra, the Nabataean tomb site and AlUla's top draw, had a little over 90,000 visitors last year, and the old town about 94,000.

The local angle

Property sales resumed in parts of AlUla in December after a long freeze. Since then, building permit requests have jumped as residents add serviced apartments and short-stay rentals.

What to watch

Who bids for the airport, and whether the commission puts a number on investment raised against its $10.9 billion goal.

Follow CapitalSA on LinkedIn for the Saudi business stories that matter →

Keep reading